Each chain link weights about 862lbs

In early 2011, a single point mooring system for a deepwater Gulf of Mexico (GOM) project failed at the tether chain for a free-standing hybrid riser[1], allowing the buoyancy air can and the free-standing flowline riser to separate. The 440-ton buoyancy air can rose suddenly to the surface while the free standing riser collapsed. Based on the investigation of this event and a review of historical events, BOEMRE is revising and re-issuing Safety Alert #259.

Root cause

After the chain had been heat treated, the non-US based manufacturer had made weld repairs to the chain by grinding defects and filling the void with weld material. The post heat treat weld repairs made the chain susceptible to hydrogen induced stress cracking due to the extreme hardness of the weld material and the residual stress within the weld.

Other similar incidents

Incident No. 1

A one-ton, 8+ inch-diameter shackle connecting a mooring system to anchoring pilings failed on an overseas floating production facility. Subsequently, an identical shackle scheduled to be used in a deepwater GOM production facility also failed catastrophically under test loads below specifications. Operator reviews of the manufacturing and testing procedure and additional material testing indicated that all of the shackles were possibly defective.

Because anchor pilings with shackles attached had already been driven, the GOM test failure required new shackles to be manufactured, new pilings installed and the replacement of portions of the mooring systems that could not be recovered. Production start-up of the facility has been delayed by at least one year.

Incident No. 2

Two sockets in a mooring system for a MODU failed under moderate loading. Testing of the remaining sockets found that others were also defective and a number of them failed catastrophically at less than specification loading.

Recommendations

The following recommendations are made by BOEMRE:

  • Operators should review their specifications requirements to insure testing and manufacturing produces a product that will meet the usage demands.
  • Operators should include sufficient Charpy testing requirements in the specifications to insure the materials and manufacturing process will produce a product of sufficient toughness.
  • Operators should review their requirements for both destructive and non-destructive testing of critical elements. Operators should insure their test coupons are properly representative.
  • Operators should review their requirements for equipment inspection and handling to insure no damaging techniques are employed in transportation or installation.
  • Operators should monitor and inspect critical mooring components 100% of the time during the manufacturing process.
  • Operators should ensure that the personnel and companies contracted to perform inspections and quality assurance of critical mooring components are qualified to do so.
  • Operators should treat the area above a buoyancy air can for a free-standing hybrid riser as potentially hazardous. No floating production facility or support vessel should be allowed to pass over a free-standing hybrid riser.


More can be found in the PDF document below.


<pdf>http://www.gomr.boemre.gov/homepg/offshore/safety/safealt/SA_296.pdf</pdf>

References

  1. http://www.gomr.boemre.gov/homepg/offshore/safety/safealt/SA_296.pdf