The Sullom Voe Terminal is an oil and liquefied gas terminal at Sullom Voe in the Shetland Islands of Scotland. It handles production from oilfields in the North Sea and East Shetland Basin. It is not a refinery and stores oil before it is transported by tanker.

Construction

When Shetland was identified as a location to provide pipeline terminal and support facilities for offshore oil installations in the northern North Sea, corporations involved had expected to each build their own terminal facilities. However, wishing to minimize the negative impacts of the industry, the Shetland Islands Council, with power granted to it by the UK Parliament in the 1974 Zetland County Council Act, was able to contain all pipeline terminal facilities at the Sullom Voe site.

Sullom Voe Terminal was built between 1975 and 1981. 6,000 people were employed during construction.[1] First oil was received at 18:40 on 25 November 1978 via the Brent pipeline. At 12:30 on 3 December 1978, the first oil from the Ninian pipeline was received. The Scatsta Airport to the south re-opened in 1978 to support the building of the terminal.

The terminal was officially opened on Saturday 9 May 1981 by Queen Elizabeth II. A bomb blast at the power station on the terminal took place at 12.05pm on the day of the ceremony which was accredited to the IRA. No-one was injured and a boiler was damaged.

Operation

File:Sullom Voe.jpg
Sullom Voe oil terminal at dusk

Sullom Voe Terminal has been owned since its construction by the Ninian and Brent partners. The plant is operated by BP. The manager of the terminal is Lindsay Boswell.

The terminal receives oil through the Brent (Shell/Esso) and Ninian (BP) pipeline systems.[2] Oil from the Schiehallion oilfield and Foinaven oilfield has been received by the purpose-built Loch Rannoch shuttle tanker since August 1998. In the late 1990s at the height of North Sea Oil, the terminal handled over a quarter of UK petroleum production and around 500 people worked there. Around half are BP workers. A new 22 inches (560 mm) pipeline was laid from the Clair oilfield in 2003-2004, and first oil from the Clair field was received in February 2005. 7 billion barrels (abt 960 million tons) of oil through the SVT achieved in December 2001. (http://www.bp.com/liveassets/bp_internet/globalbp/STAGING/global_assets/downloads/S/scotland_sullom_voe_terminal.pdf) By 2008, the terminal had handled almost 8 billion barrels (abt 1.1 billion metric tons) of oil.

Gas is imported through the West of Shetland pipeline.[2] Some of the gas is used as fuel in the Fortum operated Sullom Voe power station. The remainder is enriched with LPGs and exported to the Magnus platform for enhanced oil recovery.

Due to its secluded position, the site has its own fire brigade.[2]

Sullom Voe power station

The gas turbine power station provides electricity for around 43% of the Shetland Islands (since the early 1990s) and the other half comes from the (fuel oil-powered) Lerwick Power Station situated at Gremista. Shetland requires about 50 MWe in the winter. Since May 2004 it has been operated by the Finnish company Fortum; previous to that it was operated by BP. The 100 MWe plant has four 25 MW General Electric Frame 5 gas turbines and is part of a CHP system being built in the late 1970s. The actual power output from the plant is around 80 MWe as each turbine runs at about 18 MW. When the oil terminal was at the height of its production, 70 MWe would be used from five gas turbines by the plant, but less is needed now. It employs around twenty people.