Hybrid Risers
Hybrid risers (HRs) consist of a vertical bundle of steel pipes supported by external buoyancy. Flexible jumpers connecting the top of the riser and the vessel are used to accommodate relative motion between the vessel and riser bundle. The first use of hybrid risers was a deepwater production riser installed in 1988 in the Green Canyon Block 29 (GC29) by Cameron (Fisher and Berner).
In this subsection, we present the current hybrid riser concept including the following main components:
- Riser base foundation;
- Riser base spools;
- Top and bottom transition fogging;
- Riser cross section;
- Buoyancy tank;
- Flexible jumper between the top of the riser and the hang-off point in the FPS.
Contents
- 1 Riser Foundation
- 2 Riser Base Spools
- 3 Top and Bottom Transition Forging
- 4 Riser Cross Section
- 5 Buoyancy Tank
- 6 Flexible Jumpers and Hook Up to Vessel
- 7 Sizing of Hybrid Risers
- 8 Sizing of Flexible Jumpers
- 9 Preliminary Analysis
- 10 Strength Analysis
- 11 Fatigue Analysis
- 12 Riser Hydrostatic Pressure Test
- 13 References
Riser Foundation
The foundation structure for the HR consists of a steel suction anchor (and/or a gravity base) that will support the HR installation aids (such as pulling winches) and the flex element (a roto-latch connector is proposed). Two riser base foundation approaches are possible:
- Pinned riser base: This type of riser base allows free riser rotation.
- Fixed riser base: This type of riser base resists riser rotation.
Riser Base Spools
The riser base spool is designed to allow for relative displacements between the HR base and the flowline that may be caused by the thermal expansion of the flowline or/and angular movements (due to environmental loading) at the HR base. For the common use of a pinned riser base, the receptacle for the flex element is inclined to optimize the design of the bundle connection to its base. At the bottom of the hybrid riser, a forged Y-shaped tee allows:
- Vertical sections to be connected to the flex element;
- Lateral branch to be ended by a CVC to the rigid jumper spool.
Top and Bottom Transition Forging
Transition forging on the bottom of the riser connects the standard riser to the flowline spool. A short thickened-wall section of pipe (adapter joint), typically 3 m long, provides a transition between the standard riser pipe and the large stiffness of the riser top assembly. A flanged connection mates with the flow spool that connects the flexible jumper and the standard riser.
Riser Cross Section
The two most important factors for describing the riser cross section are the wall thickness of the riser pipe and corrosion coatings and anodes.
Buoyancy Tank
A steel structured buoyancy tank is designed based on the following functional requirements:
- To thrust the HR dead weight.
- To provide sufficient pulling tension for the dynamic equilibrium of the HR.
- To limit maximum angular deflection of the HR with regards to its static position.
The riser is tensioned by means of an air or nitrogen-filled buoyancy tank. The tank contains a number of individual compartments separated by bulkheads. The bulkheads contain stiffeners arranged on the underside of each bulkhead plate to provide additional reinforcement. The buoyancy tank is designed to be pressure balanced with the external pressure of the water; this allows the thickness of the buoyancy tank skin to be limited to a minimal wall thickness.
Flexible Jumpers and Hook Up to Vessel
Flexible jumpers connecting the top of the riser and the vessel are used to accommodate relative motion between the vessel and riser bundle. Flexible pipe jumpers are used to connect goosenecks, located immediately below the air can and the vessel.
Sizing of Hybrid Risers
The key design issues for the arrangement/sizing of the hybrid riser include:
- Overall arrangement: footprints at bases, hang-off locations/spacing;
- General arrangement:
- Riser thickness determination;
- Riser top: jumper with the characteristics and geometry of end fittings, geometry for the buoyancy tank;
- Riser base: forging and foundation;
- Sizing of buoyancy tank and suction anchor;
- Sizing of rigid jumper spool (at hybrid riser base) connected to the gas export pipeline via collect connectors.
The riser system is sized so that:
- Tethering tension is equivalent to what can be obtained from available equipment.
- Distributed buoyancy is equivalent to what is needed for neutral buoyancy in production mode.
- The upper air can provides enough buoyancy to give nominal overpull at the riser base.
- Flexible jumper hoses have sufficient length to accommodate relative vertical movement between the riser and platform at maximum drift-off position.
Sizing of Flexible Jumpers
Flowline jumpers are used to connect the riser base with the flowline base. The flowline jumpers are conventional subsea technology requiring five diameter bends for pigging.Preliminary Analysis
The key objective of the preliminary analysis is to get an indication of the requirements for:
- Buoyancy and tension distribution along the riser;
- VIV suppression devices.
Preliminary analysis is performed in two steps:
1. Static analysis to determine response to currents and vessel displacement conditions;
2. Time-domain regular wave analysis to determine response to timevarying loading.
Strength Analysis
The strength analysis should be conducted to optimize the following items for a range of possible loading conditions:
- Distributed buoyancy requirements;
- Top tension;
- Tethering tension (if any);
- Foundation loading.
The loading conditions include:
- Extreme waves;
- Extreme currents;
- Extreme vessel drift;
- Winds and currents from opposing directions.
Fatigue Analysis
Like any other riser analysis, a fatigue analysis for a hybrid riser should include vessel drift motions, first-order wave action, and VIV and installation-induced fatigue. VIV analysis of hybrid risers may consider current profiles of varying levels, up to and including 100-year return currents. The total VIV fatigue damage can then be calculated using the damage from each profile and the associated percentage occurrence.
Riser Hydrostatic Pressure Test
A pressure test must be carried out before any riser commences operation. The filling, cleaning, gauging, batching, logging, dewatering, and hydrostatic pressure testing operations of the riser system should be performed in accordance with the requirements of DNV OS F101 and other relevant codes.
The sequence of pressure testing operations for a riser system is as follows:
- Filling;
- Cleaning and gauging;
- Hydrotesting, including temperature stabilization, pressurization, air contents check, and hydrostatic test/holding period;
- Post-testing, including depressurization and documentation;
- Rectification activities (if required), including leak location during test, dewatering for rectification, and rectification of defects;
- Final/repeat hydrotesting;
- Testing, certificates, and witnessed signature.
References
[1] Y. Bai, Q. Bai, Subsea Pipelines and Risers, Elsevier, Oxford, 2005.
[2] American Bureau of Shipping, Guide for Building and Classing: Subsea Pipeline Systems and Risers, ABS (March, 2001)
[3] T. McCardle, Subsea Systems and Field Development Considerations, SUT Subsea Awareness Course, 2008.
[4] American Petroleum Institute, Recommended Practice for Flexible Pipe, API RP 17B, (2002).
[5] American Petroleum Institute, Specification for Unbonded Flexible Pipe, API Specification 17J, (1999).
[6] American Petroleum Institute, Design of Risers for Floating Production Systems (FPSs) and Tension-Leg Platforms (TLPs), API RP 2RD, ( June, 1998).
[7] R. Burke, TTR Design and Analysis Methods, Deepwater Riser Engineering Course, Clarion Technical Conferences, (2004).
[8] World Oil, Composite Catalog of Oilfield Equipment & Services, Fourty Fifth ed., 2002, March.
[9] G. Wald, Hybrid Riser Systems, Deepwater Riser Engineering Course, Clarion Technical Conferences, 2004.
[10] S. Chakrabarti, Handbook of Offshore Engineering, Ocean Engineering Book Series, Elsevier, Oxford, 2005.
[11] V. Alliot, J.L. Legras, D. Perinet, A Comparison between Steel Catenary Riser and Hybrid Riser Towers for Deepwater Field Developments, Deep Oil Technology Conference. (2004).
[12] L. Deserts, Hybrid Riser for Deepwater Offshore Africa, OTC 11875, Offshore Technology Conference, Houston, Texas (2000)
[13] E.A. Fisher, P. Holley, S. Brashier, Development and Deployment of a Freestanding Production Riser in the Gulf of Mexico, OTC 7770, Proc. 27th Offshore Technology Conference, Houston, (1995).
[14] C.T. Gore, B.B. Mekha, Common Sense Requirements (CSRs) for Steel Catenary Risers (SCR), OTC 14153, Offshore Technology Conference, Houston, Texas, (2002).
[15] American Petroleum Institute, Specification for Line Pipe, API Specification 5L, fourty second ed., (2000).
[16] F. Kopp, B.D. Light, T.S. Preli, V.S. Rao, K.H. Stingl, Design and Installation of the Na Kika Export Pipelines, Flowlines and Risers, OTC 16703, Offshore Technology Conference, Houston, Texas, (2004).
[17] R. Franciss, Vortex Induced Vibration Monitoring System in Steel Catenary Riser of P-18 Semi-Submersible Platform, OMAE2001/OFT-1164, Proceedings of OMAE’01 (2001).
[18] E.H. Phifer, F. Kopp, R.C. Swanson, D.W. Allen, C.G. Langner, Design and Installation of Auger Steel Catenary Risers, OTC 7620, Offshore Technology Conference, Houston, Texas, (1994).
[19] G. Chaudhury, J. Kennefick, Design, Testing, and Installation of Steel Catenary Risers, OTC 10980, Offshore Technology Conference, Houston, Texas, (1999).
[20] H.M. Thompson, F.W. Grealish, R.D. Young, H.K. Wang, Typhoon Steel Catenary Risers: As-Built Design and Verification, OTC 14126, Offshore Technology Conference, Houston, Texas, (2002).
[21] K. Huang, X. Chen, C.T. Kwan, The Impact of Vortex-Induced Motions on Mooring System Design for Spar-Based Installations, OTC 15245, Offshore Technology Conference, Houston, Texas, (2003).
[22] M. Hogan, Flexjoints, ASME ETCE SCR Workshop, Houston, Texas, 2002, February.
[23] J. Buitrago, M.S. Weir, Experimental Fatigue Evaluation of Deepwater Risers in Mild Sour Service, Deep Offshore Technology Conference, Louisiana, New Orleans, (2002).
[24] International Standards Organization, Petroleum and Natural Gas Industries Design and Operation of Subsea Production Systems, Part 7: Completion/Workover Riser Systems, ISO 13628–7: 2005, (2005).
[25] R. Jordan, J. Otten, D. Trent, P. Cao, Matterhorn TLP Dry-Tree Production Risers, OTC 16608, Offshore Technology Conference, Houston, Texas, (2004). [26] A. Yu, T. Allen, M. Leung, An Alternative Dry Tree System for Deepwater Spar Applications, Deep Oil Technology Conference, New Orleans, (2004).
[27] Massachusetts Institute of Technology, User Guide for SHEAR7, Version 2.0, Department of Ocean Engineering, 1996.
[28] Massachusetts Institute of Technology, SHEAR7 Program Theoretical Manual, Department of Ocean Engineering, 1995.
[29] Y. Zhang, B. Chen, L. Qiu, T. Hill, M. Case, State of the Art Analytical Tools Improve Optimization of Unbonded Flexible Pipes for Deepwater Environments, OTC 15169, Offshore Technology Conference, Houston, Texas, (2003).
[30] J. Remery, R. Gallard, B. Balague, Design and Qualification Testing of a Flexible Riser for 10,000 psi and 6300 ft WD for the Gulf of Mexico, Deep Oil Technology Conference, Louisiana, New Orleans, (2004).
[31] B. Seymour, H. Zhang, C. Wibner, Integrated Riser and Mooring Design for the P-43 and P-48 FPSOs, OTC 15140, Offshore Technology Conference, Houston, Texas, (2003).
[32] P. Elman, R. Alvim, Development of a Failure Detection System for Flexible Risers, 18th International Offshore and Polar Engineering Conference, (2008).
[33] D.E. Thrall, R.L. Poklandnik, Garden Banks 388 Deepwater Production Riser Structural and Environmental Monitoring System, OTC 7751, Proc. of the 27th Offshore Technology Conference, Houston, Texas, (1995).
[34] L. Deserts, Hybrid Riser for Deepwater Offshore Africa, OTC 11875, Offshore Technology Conference, Houston, Texas, (2000).
[35] M. Wu, P. Jacob, J.F.S. Marcoux, V. Birch, The Dynamics of Flexible Jumpers Connecting A Turret Moored FPSO to A Hybrid Riser Tower, Proceedings of D.O.T XVlll Conference, (2006).
[36] J.K. Vandiver, L Li, User Guide for SHEAR7, Version 2.1 & 2.2, for Vortex-Induced Vibration Response Prediction of Beams or Cables with Slowly Varying Tension In Sheared or Uniform Flow, Massachusetts Institute of Technology, 1998.
[37] J.K. Vandiver, Research Challenges in the Vortex-Induced Vibration Prediction of Marine Risers, Offshore Technology Conference, Houston, Texas, (1998).